| Location |
Status |
Update |
Wisconsin DOT Utilities and Paving
|
|
|
| |
|
|
| Capitol Drive (84th St. to Mayfair Rd.) |
The contract is in the design phase to be let out to construction in March. Construction should begin in May of 2013.
|
March 2, 2013 |
| Mayfair Road (I-94 to Watertown Plank Rd.) |
Construction has begun on the paving project. Currently the contractor is constructing temporary lanes as well as grading for future construction on the east side of the roadway progressing from south to north. Most of the private utility installations are installed. The contractor will be placing new storm sewer on the east side of the roadway as well as some sanitary and watermain installations in the area.
|
April 1, 2013 |
| Glenview Avenue (Hawthorne Ave. to North of Wisconsin Ave.) |
The contractor continues to place watermains on the project currently between Hill St. and Blue Mound Rd. proceeding to the north. Once the watermain is complete it must pass a series of tests and then individual water services will be placed on the roadway. Also we will have some private utility companies working on installations on the roadway prior to the WisDOT paving project which will include paving from I-94 to Blue Mound Rd. and completely repaving the roadway between Blue Mound Rd. and Avon Ct.
|
April 1, 2013 |
| |
|
|
Utilities and Paving
|
|
|
Meinecke Avenue (Swan Blvd. to 81st St.)
Ald. Roznowski's Newsletter
Resident Notification Letter |
The contractor has completed the street light work on the roadway waiting for a better trend in the weather to begin any other work that needs to be done. The contractor will be doing a pump station modification between 85th and 86th Sts. followed by some paving work to complete the work that was done last year.
Beginning this week and continuing through May, the plan is to complete the remaining tasks of the Meinecke/90th St project. Weather will always be a factor, as it has been in beginning this final phase of the project.
• This Wednesday, May 1, tree planting is planned to start
• Beginning the week of May 6, the pump station at 86th and Meinecke will be re-connected from the storm pipe to the sanitary pipe
• Beginning the week of May 16, street paving will begin along Meinecke, between 90th and Swan
o Parking passes will be distributed this week
o Manhole alignment, removal of the temporary asphalt adjacent to the curbs and the pouring of the final layer of asphalt will also occur along Meinecke and 90th St.
o 86th St between Meinecke and Wright will also have asphalt laid, likely in late May
• There will also be concrete work for some driveways, service walks and sidewalk squares
• Sod production at sod farms was severely impacted by the late winter and wet April so I do not have a date yet on the laying of sod but the plan is also to have that occur in May
• The old street lights will be removed
Our contractor, Globe, expects this activity to last about 30 days
Please click here |
April 1, 2013
April 29, 2013
May 6, 2013
|
| 90th Street (North Ave. to Meinecke Ave.) |
The contractor will be starting paving sometime in April weather permitting. Paving will include milling and repaving the center part of the roadway.
|
April 1, 2013 |
| 124th Street (Watertown Plank Rd. to Garfield Ave.) |
The roadway will be repaved beginning this summer.
|
April 1, 2013 |
| Center Street (117th St. to 124th St.) |
The project is currently in the design phase.
|
April 1, 2013 |
| Chambers Street (120th St. to 124th St.) |
The project is currently in the design phase.
|
April 1, 2013 |
| Discovery Parkway (Watertown Plank Rd. to swan Blvd.) |
The contractor continues utility work on the project as well as grading.
|
April 1, 2013 |
| |
|
|
Utilities Only
|
|
|
| Sanitary Sewer Project (Watertown Plank Rd. to Walnut Rd., 115th St. to 124th St.) |
The project is currently out for bid.
|
April 1, 2013 |
| Sanitary Sewer Project (Walnut Rd. to North Ave., 115th St. to 124th St.) |
The project is currently out for bid.
|
April 1, 2013 |
| Sanitary Sewer Project Diane Drive (120th St. to 115th St.) |
The project is currently out for bid.
|
April 1, 2013 |
Storm Sewer Project 100th Street (Grantosa Ave. to Ruby Ave.)
100th Street Detour Route |
The contractor began work on the sanitary sewer relay this week at Grantosa Ave. proceeding from south to north. Once the sanitary sewer and watermain alterations are made they will begin the installation of the larger diamater storm sewer proceeding from south to north.
|
April 1, 2013 |
| Watermain Glenview Avenue (Hawthorne Ave. to Avon Ct.) |
The contractor is presently in the Blue Mound Rd. intersection. The next phase of construction will be from Blue Mound Rd. to Avon Ct. due to the narrow roadway the contractor will need to flag traffic in one direction during some operations. There will be traffic delays in this area. Once the contractor is through to Avon Ct. there will be a series of testing on the watermain and athe individual services will be attached.
|
April 1, 2013
|
| Watermain Harwood Avenue (Dewey Ave. to Glenview Ave.) |
The contractor expects to begin sometime in late April.
|
April 1, 2013 |
Sanitary Sewer Project Ravenswood Area
|
The contractor continues to install sanitary sewer pipe proceeding generally to the northwest then will begin work on Glencoe Cir.
|
April 1, 2013
|