| Location |
Status |
Update |
Wisconsin DOT Utilities and Paving
|
|
|
| |
|
|
| Capitol Drive (84th St. to Mayfair Rd.) |
The contractor is currently doing milling and pavement removal on the north side of the roadway progressing from east to west. Also the contractor began work on the bridge on the north side of the roadway over Grantosa Creek which will be rebuilt. Once the paving and bridge work is complete the contractor will reverse the traffic flow onto the north side of the roadway and work on the south side of the roadway. Construction is expected to last until November of 2013.
|
June 15, 2013 |
| Mayfair Road (I-94 to Watertown Plank Rd.) |
The contractor continues work on the east side of the roadway. The contractor is widening the roadway to the east presently doing grading work, storm sewer work, sanitary sewer work, and water main alterations on the roadway as well as some retention pond construction. Once the east side of the roadway is compete they will switch traffic over and work on the west side of the roadway. Construction is expected to last into November of 2013.
|
June 15, 2013 |
| Glenview Avenue (Hawthorne Ave. to North of Wisconsin Ave.) |
The water main contractor completed work between Hawthorne Ave. and Blue Mound Rd. They will also be doing some restoration from Hawthorne Ave. to St. Jude Ct. Also there are some utility companies doing work in that area - mainly around Blue Mound Rd. They will be completing their work shortly and the DOT paving contractor will begin work mainly in the Blue Mound Rd. intersection.
|
June 15, 2013 |
| |
|
|
Utilities and Paving
|
|
|
Meinecke Avenue (Swan Blvd. to 81st St.)
|
Week of June 17th
Landscaping, finish paving and other miscellaneous work.
The contractor is responsible for water the newly placed sod for the first 5 days. After that it becomes the homeowner's responsibility to water.
Construction is expected to be completed June 21st weather permitting.
Thank you for all your patience and cooperation as this project comes an end.
|
June 15, 2013
|
| 90th Street (North Ave. to Meinecke Ave.) |
The contractor completed tree replacement on 90th St. beginning from Menomonee River Pkwy. and will proceed to the north on 90th St. Also the contractor has resumed work on some of the facilities on Meinecke Ave.
|
June 15, 2013 |
124th Street (Watertown Plank Rd. to Garfield Ave.)
|
Underground utility work should begin soon.
|
June 15, 2013 |
| Center Street (117th St. to 124th St.) |
Underground utility work should begin soon.
|
June 15, 2013 |
| Chambers Street (120th St. to 124th St.) |
Underground utility work should begin soon.
|
June 15, 2013 |
| Discovery Parkway (Watertown Plank Rd. to swan Blvd.) |
The contractor continues to grade on the site and has installed several infrastructure utilities and will continue to do that. Paving on the roadway will most likely take place in July of 2013. The roadway is scheduled to be opened in early fall.
|
June 15, 2013 |
| |
|
|
Utilities Only
|
|
|
Sanitary Sewer Project (Watertown Plank Rd. to Walnut Rd., 115th St. to 124th St.)
|
Work should begin in late July.
|
June 15, 2013 |
| Sanitary Sewer Project (Walnut Rd. to North Ave., 115th St. to 124th St.) |
Work should begin in late July.
|
June 15, 2013 |
| Sanitary Sewer Project Diane Drive (120th St. to 115th St.) |
Work should begin in late July.
|
June 15, 2013 |
Storm Sewer Project 100th Street (Grantosa Ave. to Ruby Ave.)
Link to 100th Street Detour Route
|
The contractor has done storm sewer installation from Grantosa Creek progressing to the north. The contract is expected to be completed some time in October, 2013.
|
June 15, 2013 |
Water Main Glenview Avenue (Hawthorne Ave. to Avon Ct.)
|
Construction is complete.
|
June 15, 2013
|
| Water Main Harwood Avenue (Dewey Ave. to Glenview Ave.) |
The contractor has postponed construction until late August due to some detours that the DOT has set up due to the Glenview Ave. I-94 Zoo Interchange project.
|
June 15, 2013 |
Sanitary Sewer Project Ravenswood Area
|
Project is complete. |
June 15, 2013
|